Airports and Runways

Grand Bahama International Airport

BHM was appointed Main Contractor for the runway rehabilitation works. The upgrade to the runway to ensure compliance with ICAO requirements and to provide significant future lifespan without requiring major maintenance.

Client: Grand Bahama International Airport

The runway was in poor condition as the area was prone to significant weather events, including flooding and storms and having had no major rehabilitation works since 2002 / 2003. The runway was showing distresses including:
Opening and separation of paving joint lines
General weathering and raveling of the wearing course
Depressions, cracking and heaving

The runway was not in full compliance with ICAO regulations, requiring a number of significant upgrades.

BHM was appointed Main Contractor for the runway rehabilitation works. The upgrade to the runway to ensure compliance with ICAO requirements and to provide significant future lifespan without requiring major maintenance. scope including:

• Profile milling and paving using 2d and 3d laser guided leveling system
Installed new AGL system for entire runway
Installed new longitudinal drainage runs on both sides of runway
Reinstated all runway markings with upgrades to ensure ICAO compliance

Services Provided

Profile Milling and paving (P-401 mix) to resurface a 3,359m long by 47.5m wide, international runway whilst the runway remained fully operational
Utilized bitumen grades 76-22 with elastic recovery of 70%
Installed new inset LED AGL lighting and control system
Risk management and reduction
Value engineering & Collaboration with engineers, suppliers and other parties

Customer Benefits

Risk Management: De-risking original design and methodology to include for displaced thresholds allowing 24 hour working at each end of the runway, without restricting air traffic.
Value Engineering: providing alternative methodologies to de-risk the project and providing cost savings to the customer – such as the displaced threshold arrangement
No interruption to any flights during the works, including night-time medi-vac flights
Works carried out to ensure compliance with International Civil Aviation Organization airfield requirements
Lump Sum Contract provided cost certainty, with Contract delivered on time and on budget
Fast mobilization with equipment transported from 3 islands, including 2 mobile asphalt plants