BHM carried out these works for the Ministry of Public Works and Transport as part of the Island wide Nassau Road Improvement project.
Client: Ministry of Public Works and Transport
The works were carried out under strict traffic management to ensure traffic flows on the heavily congested Harrold Road artery. BHM worked closely with BEC to coordinate distribution of electrical services concurrently with our own works to minimize disruption to the general public.
The scope for this $7.7million contract included:
• Site clearance
• Bulk earthworks
• Stabilisation and base work
• Grading and profiling
• Road drainage including gullies and swales
• Installation of utility and BEC service ducts
• Construction of new side walks
• Hot mix asphalt road construction
• Thermo plastic road markings
• Hard and soft landscaping
• Street lighting
Services Provided
• Risk Management
• Construction management
• Design management of surfacing materials
• Traffic management
Customer Benefits
• Works planned to minimize disruption to local business and road users
• Single point of contact for client team
• Coordination with existing roads and infrastructure
• In house plant, materials and testing